By now everyone is aware of the US20 expansion project that
will be taking place from CR17 in Elkhart to SR15 in Bristol. Last week I
attended pre-construction meeting to meet with individuals from INDOT as well
as Niblock, the company awarded the project.
Below, I have listed some of the main takeaway points from the meeting.
- · Expect to see work beginning sometime during this week. The Right-of-Way is scheduled to be staked and tree removal will begin.
- · The goal is to minimize any road closures of county roads connecting to US20, but some temporary and intermittent closures will be necessary. This includes CR21. There are no specific dates set for closures, so be prepared for this possibility if you use US20 and CR21 to travel to Elcona.
- · You should fully expect an increase in traffic along CR21 due to motorists wanting to use it as a short cut when traffic is slow on US20. Please use caution when coming in and out of the club and when crossing CR21 with a golf cart.
- · This project is not expected to be completed until the latter part of 2014. The south side of the expansion will be done in 2013 with the north side completed in 2014.
- · There will be minimal disruption to Elcona’s property. A few trees are expected to be removed at the intersection of CR21 and US20 but, beyond that, no other major removal is expected. Our fence along #2 and #15 will remain intact and the sign and landscaping along US20 should remain undisturbed.
- · Major earthmoving will not begin until 6/10
Please let me know if you have additional questions.